IEBC Compliance Methods


Summary

The IEBC offers three ways to show an existing building project complies: the prescriptive method, the work area method, and the performance method with its numerical scoring. The project follows one method, and the choice sets which chapters apply and how much of the building must be upgraded, so choose it at the start of design.


Cols

Scope

Terminology

Requirements

Chapter 3, provisions for all methods

Section Title
301 Administration
302 General provisions
303 Storm shelters
304 Structural design loads and evaluation and design procedures
305 In-situ load tests
306 Accessibility for existing buildings
307 Smoke alarms
308 Carbon monoxide detection

The three methods

Method Chapters Approach
Prescriptive 5 Direct requirements for additions (502), alterations (503), fire escapes (504), windows and emergency escape openings (505), change of occupancy (506), and historic buildings (507)
Work area 6 through 12 Classify the work (Chapter 6) as Level 1 (Chapter 7), Level 2 (Chapter 8), or Level 3 (Chapter 9), with change of occupancy (Chapter 10), additions (Chapter 11), and historic buildings (Chapter 12)
Performance 13 Evaluate the existing building with a numerical scoring system covering 21 safety parameters and the degree of compliance of each, to show that alterations improve the existing situation

Authority

Worked examples

Choosing a method

Project Likely method Reason
Replace finishes and fixtures in an office floor with no layout changes Work area method, Level 1 Limited, clear scope
Reconfigure partitions on three floors of an older office building Work area method, Level 2 or 3 Scales requirements to the area changed
Small addition and a few alterations to a small building Prescriptive method Direct rules in one chapter
Older building that cannot meet code for an alteration, with unusual conditions Performance method Scoring demonstrates equivalent safety
Change from office to restaurant Work area (Chapter 10) or prescriptive (506) Depends on the jurisdiction and building

Documenting the method

Item Where it goes
Method selected Code analysis sheet
Work area boundaries and percent of the building Plan diagram and the area table
Level of alteration Code analysis sheet
Chapter 3 items (accessibility, smoke alarms, structural) Checklist in the plan set