NEC Working Space and Equipment Clearances


Summary

The NEC requires clear working space in front of switchboards, panelboards, and similar equipment, a dedicated space above and in front of it, and set door and entrance arrangements for larger gear. Electrical rooms are routinely drawn too small, so size them from these dimensions before shafts, corridors, and adjacent rooms are fixed.


Cols

Scope

Terminology

Requirements

Working space

Entrances and doors

Illumination and dedicated space

Worked examples

Panelboard room

A 480Y/277 V panelboard, 20 in. wide, on a concrete wall with a switchboard facing it across the room.

Step Check Result
Voltage to ground 277 V, in the 151 to 600 V band Table 110.26(A)(1) applies
Condition Live parts on one side and grounded concrete behind the other (Condition 2) or live gear opposite (Condition 3) 3-1/2 ft or 4 ft depth
Width Greater of 30 in. and 20 in. 30 in.
Height 6-1/2 ft clear Pipes and ducts kept out
Dedicated space 20 in. wide by equipment depth, 6 ft above No pipes or ducts above the panel

Large switchboard

A 2,000 A switchboard 8 ft wide.

Step Check Result
Entrance Over 6 ft wide and 1,200 A or more 24 in. by 6-1/2 ft entrance at each end of the working space
Door Equipment rated 800 A or more, door less than 25 ft from the working space Door opens out in the direction of egress with panic hardware
Working space Depth by condition, width at least 8 ft Room at least the working depth plus the gear depth
2026 24 in. egress path at a 90 degree door opening Lay out the door swing and the gear to keep the path

Room sizing

Item Value
Gear depth 30 in. (2-1/2 ft)
Working depth, Condition 1 3 ft
Room depth, one side of gear 5-1/2 ft
Gear on both walls, facing Add both gear depths and the working depth between, which is at least 4 ft for Condition 3

Coordination

Common issues

Standards

Sources