IECC Air Barrier Requirements


Summary

The IECC requires the building envelope to be sealed against air leakage: a continuous air barrier in commercial buildings and a tested leakage limit in dwellings. The air barrier is a continuity detail across materials, joints, and penetrations, so decide where it sits at the start of wall and roof design and carry it through every transition.


Cols

Scope

Terminology

Requirements

Commercial

Residential

Worked examples

ACH50 from a blower door result

A 2,000 sq ft house with 9 ft ceilings (18,000 cu ft) tests at 1,500 CFM50.

Step Calculation Result
Volume 2,000 × 9 18,000 cu ft
Air changes at 50 pascals 1,500 × 60 ÷ 18,000 5.0 ACH50
Limit, climate zone 3 to 8 3 ACH50 Fails
Allowed leakage 3 × 18,000 ÷ 60 900 CFM50
Reduction needed 1,500 − 900 600 CFM50, or 40 percent

Where the barrier sits

Layer option Detail Coordination
Fluid-applied membrane on sheathing Continuous over sheathing and window openings Taped transitions at roof and foundation
Taped sheathing Sealed joints Seal at penetrations
Interior drywall approach Gasket at plates and boxes Sealed outlet boxes

Transition checklist

Transition Action
Wall to roof Lap the wall barrier into the roof membrane
Wall to window Seal the frame to the barrier with flashing tape or sealant
Wall to foundation Seal the sill plate or slab edge
Penetrations Sleeve and seal pipes and ducts

Coordination

Common issues

Standards

Sources