Site Plan Review and Entitlements


Summary

Site plan review and entitlements are the local approvals a project needs before a building permit: staff review of the site plan, and where required a rezoning, conditional use permit, variance, or other hearing. The path, fees, and time depend on what the project needs, so identify the approvals in the first meeting with planning staff and carry their schedule into the project plan.


Cols

Scope

Terminology

Requirements

Typical steps

  1. Pre-application meeting: some cities offer a free conceptual review that helps expedite approval
  2. Application and completeness check: the planning department confirms the submittal is complete and routes it to other departments such as engineering, fire, and utilities
  3. Staff review: comments are collected and returned to the applicant; staff makes a recommendation to approve, approve with conditions, or deny
  4. Decision: administratively by staff, or by the planning commission after a public hearing; the body may approve, approve with conditions, postpone, or deny
  5. Revisions and conditions: the applicant revises plans to reflect conditions; approval is typically documented in a letter and the plan is stamped
  6. Handoff: planning staff forwards the approved plan to the building division for permit review
  7. Expiration: approved plans lapse if the project does not proceed within the stated period and must be resubmitted

Timelines

Typical site plan contents

Worked examples

Schedule from approvals

A mixed-use project in a district where the restaurant is a conditional use.

Stage Path Schedule note
Pre-application Meeting with staff Identifies the conditional use early
Application and completeness Submittal, routing Clock starts when the application is complete
Staff review and comments Return and resubmit Each resubmittal adds a review cycle
Conditional use hearing and commission decision Notice, hearing Fixed by the commission's meeting dates and notice period
Revisions and approval letter Conditions Plans revised to match conditions
Building permit review After planning approval Per the building department

The conditional restaurant moves the project from administrative review to the hearing path, which lengthens the schedule.

Zoning data table

For a 10,000 sq ft lot in a district with illustrative standards.

Item Required Proposed Complies
Lot area 6,000 sq ft minimum 10,000 sq ft Yes
Floor area ratio 1.5 maximum 1.4 (14,000 sq ft) Yes
Lot coverage 60 percent maximum 55 percent (5,500 sq ft) Yes
Height 45 ft maximum 42 ft Yes
Parking Per the ordinance's ratios 43 spaces Compare against the calculated count

Coordination

Common issues

Standards